Education
-
2012 - 2016
Jobs in Indonesia
Bachelor's degree, Civil Engineering
Activities and societies: Secretary of BEM FT 2014-2015, Publication Division of PEMIRA 2013, Engineering Geology Lecturer Asistant 2014 - 2015, Highway Engineering Lecturer Asistant 2015, Physic Laboratory Asistant 2014, Surveying Laboratory Asistant 2015
Experience
-
2024 - Present
Xavier Knight
Undergraduate Facade Engineer
-
2024 - 2024
Xavier Knight
Facade Engineer Intern
- 2023 - 2023
-
2019 - 2023
PT KOI Café Indonesia
Project Estimator
• Performed an expenses audit on new outlet construction.
• Performed a negotiation of unit price for main contractor. Successfully prevented over spending (± IDR 200 million) because of the overprice proposal from contractor. -
2020 - 2021
PT KOI Café Indonesia
Associate Analyst - Logistic & Marketing Dept.
• Developed Dashboard Sales for 72 outlets to provide insight for management such as Sales Trend by Area, Category, Promotion using Ms. Excel and Ms. Power BI.
• Created automated Inventory Report for End-Month Closing using excel by leveraging the following functions/formulas: Pivot Table, VBA Script, Vlookup, HLookup, Conditional Function (IF, SUMIF, IFS, AVERAGEIF) thus resulting in reduction time up to 30% in the manual effort of report creation. -
2019 - 2019
RADJACORP Group
Senior Civil Engineer
• Conducted site visit and gathering requirement for Water Treatment Project in North Konawe – Southeast Sulawesi.
• Finished final verification for Transmission Line 70 kV Dukong – Manggar Section 1 Project in Belitung – Bangka Belitung. -
2018 - 2019
PT Paramita Bangun Sarana Tbk
Cost Control Engineer
• Performed an expenses audit on material purchases and work opname.
• Performed a negotiation of labour unit price and created work order for sub contractor.
• Analyzed over budget calculation. Successfully prevented over spending because of Site Engineer’s miscalculation with value ± IDR 20 million. -
2017 - 2018
PT Paramita Bangun Sarana Tbk
Engineer
• Resolved design and development problems of the Refinery & Fractionation Lampung Project (± 1.554 m2) and Hazardous & Toxic Subtances Waste Storage Marunda Project (± 386.5 m2)
• Scheduled material purchases and deliveries of the Refinery & Fractionation Lampung Project and also controlled material specification. Successfully using gradual purchasing strategy to save 480 meter square ceramic floor with value ± IDR 70 million. -
2016 - 2017
PT Bangun Prima Sentosa
Junior Engineer
• Created construction drawing (Using Autocad) for labour dorm project (± 994 m2). Construction drawing can be implemented immediately by site engineer on time.
• Calculated material needs for Green Garden, Pantai Mutiara and Kelapa Gading Resident. -
2015 - 2016
PT. Grafos GrahaPersada
Intern
Hotel Amaris Padang Project (9 stories, ±1.564 m2)
• Calculated concrete, reinforcement bar, formwork needs based on for construction drawing.
• Created Bar Bending Schedule for simplify rebar fabrication.